WHEN THE 7th CAST IN-SITU SPAN GOT IT FIRST LIFT, THE COMPLETED WORK PERCENTAGE OF CIS PROGRESS IS NOW UP TO 48.86 %. NOT MUCH HAPPEN AT CIS I AS ONLY WORK DONE FOR SPAN LOWERING, BUT MOST ATTENTION PAID ON CIS II. PP144-PP145 IS NOW ON PROGRESS FOR COMPLETING THE REST REBARS BEFORE THE SECOND LIFT OF CONCRETE LAYERED ON IT. ALL SET OF OUTER SHUTTERS HAVE BEEN ERECTED ON PP141-PP142 AND THE REBARS IS NOW RUNNING ON. APPROXIAMATELY, CRIBS INSTALLATION FOR SPAN PP140-PP141 WAS COMPLETED.