THIS IS AN UNOFFICIAL BLOG OF BC9 PROJECT

.

Monday, December 15, 2008

CIS GOT 1 MORE

Photo 1 : PP146A-PP147A, ready to be lowered.

Photo 2 : PP143-PP144 before casting.

Photo 3 : PP143-PP144 after casting, is on curing period.


Photo 4 : PP137A-P138A is ready to receive its weight.

ONE MORE SPAN AT CAST IN-SITU SITE, CUMMULATIVELY 11 SPANS CASTED. THE SECOND LAYER CONCRETE POURED YESTERDAY DEC13 ON SPAN PP143A-PP144A. MEANWHILE, THE LAST SPAN OF CIS I IS PLANNED FOR ITS 1st CASTING AROUND THIS WEEK BECAUSE MOST OF THE REINFORCEMENT IS READY AND SOME OF THE INNER SHUTTERS WERE START PLACED. SO, WITH 3 BALANCES MORE, AND THE PERCENTAGE OF CIS PROGRESS IS INDICATED AS 74.67 %.

PARAPETS MOVE ON 3 PATH

PARAPET GANTRY NO.1 IS NOW REACHING THE SPAN OF P131-P132. MEANWHILE PARAPET GANTRY NO.2 IS BUSY ERECTING THE PARAPETS ON PP3-PP4. ON THE OTHER SIDE, PARAPET GANTRY NO.3 WILL BE WORKING ON THE COMPLETED SPAN CHASING LAUNCHER GIRDER NO.2 WHICH IS ON P42-P43.

CASTING UPDATE

Photo 1 : Among the balances at yard.


THE LATEST UPDATE SAYING THAT TOWARDS THE LAST EXISTED PIER ON NANGLOI RAILWAY STATION TO NANGLOI STATION OF P35, THERE ARE 10 SEGMENTS BALANCE TO CAST. CASTING OF PARAPET IS NOW BEING CONCERNED ON CURVE SPAN AND NON-STANDARD PARAPET.

Monday, December 1, 2008

INDIA ELECTION

LG NO.2 CONTINUES ITS SCHEDULE TO WORK ON NEXT SPAN AFTER BEING STOPPED DUE TO INDIA'S ELECTION ON 29th NOVEMBER IN ORDER TO AVOID ANY INCONVINIENCE CIRCUMSTANCES. AFTER AN ATTACK IN MUMBAI, SECURITY HAS BEEN EMPHASIZED FROM PUBLICS TO FACILITIES AND BUILDINGS TO CONSTRUCTION AREA. SO FAR, THERE WAS NO INCIDENT, BUT LG NO.2 IS CONCERNING ON THE COMING SPANS EVEN THE LAST 6 PIERS TOWARDS NANGLOI STATION IS STILL NOT BAING CONSTRUCTED.

LG NO.1 CLOSES ITS DIARY

Photo 1 : Front support has been de-erected.


BY STRESSING DONE AT FRIDAY NIGHT OF 28th NOVEMBER, LAUNCHING GIRDER NO.1 IS NOW BEGIN TO BE DISMANTLED. FROM RAJDHANI PARK TO MUNDKA, LG NO.1 HAD DONE 39 SPANS.