Photo 2 : PP143-PP144 before casting.
Photo 3 : PP143-PP144 after casting, is on curing period.
Photo 4 : PP137A-P138A is ready to receive its weight.
ONE MORE SPAN AT CAST IN-SITU SITE, CUMMULATIVELY 11 SPANS CASTED. THE SECOND LAYER CONCRETE POURED YESTERDAY DEC13 ON SPAN PP143A-PP144A. MEANWHILE, THE LAST SPAN OF CIS I IS PLANNED FOR ITS 1st CASTING AROUND THIS WEEK BECAUSE MOST OF THE REINFORCEMENT IS READY AND SOME OF THE INNER SHUTTERS WERE START PLACED. SO, WITH 3 BALANCES MORE, AND THE PERCENTAGE OF CIS PROGRESS IS INDICATED AS 74.67 %.
No comments:
Post a Comment