THIS IS AN UNOFFICIAL BLOG OF BC9 PROJECT

.

Monday, February 2, 2009

BUSY BATCHING PLANT

DOUBLE CONCRETE DISPATCH TO CAST IN-SITU SITE, ABOUT 40 METRE CUBES FOR EACH PARTICULAR UNDERGOING PROGRESS. PP139A-PP140A GOT ITS SECOND LAYER THEN PROCEED TO POUR FIRST LAYER CONCRETE ON SPAN OF PP143A-PP144A. ABOUT 15 TRIPS DELIVERY BY SEVERAL TRANSIT MIXERS, SO BATCHING PLANT WAS QUITE BUSY WRITTEN ON DIARY OF 31st JANUARY 2009.