GLIMPSES BY END SPRING

Photo 1 : LG No.2 finished its span and look forward for the next.

Photo 2 : Last preparation of the last pier, just next to Nangloi Station, such a very high congested area.

Photo 3 : A crane used to lift cable trough.

Photo 4 : Rail track work by another contractor.

TEMPERATURE RISES HIGHER AS SUMMER GOES BY. RECENTLY, LAUNCHING GIRDER NO.2 IS LOOKING FOR THE 4th LAST SPAN, DOING PREPARATION FOR AUTOLAUNCHING. MEANWHILE, THE LAST PIER IS COMPLETELY CASTED, STILL UNDER CURING PERIOD. NOWADAYS, TRAFFIC JAM IN NANGLOI IS FREQUENTLY OCCURS. ON TOP OF THAT, HOPEFULLY LG NO.2 WILL KEEPS ON SAFETY AGAINST MANY KIND OF RISKS.
PLACING OF CABLE TROUGH IS STILL ON GOING. CAST IN-SITU PARAPET IS BELIEVED TO BE STARTED SOON AT TWO ENDS, PARTICULARLY ON THE END OF MAIN LINE AND PORTAL PIER OF PP134. INSTEAD AT CIS II, INSTALLING OF HAND RAILING IS UNDERGOING SMOOTHLY AS THE RAIL TRACK CONTRACTOR IS BUSY ON THEIR OWN WORKS.