ONE MORE SPAN AT CAST IN-SITU SITE, CUMMULATIVELY 11 SPANS CASTED. THE SECOND LAYER CONCRETE POURED YESTERDAY DEC13 ON SPAN PP143A-PP144A. MEANWHILE, THE LAST SPAN OF CIS I IS PLANNED FOR ITS 1st CASTING AROUND THIS WEEK BECAUSE MOST OF THE REINFORCEMENT IS READY AND SOME OF THE INNER SHUTTERS WERE START PLACED. SO, WITH 3 BALANCES MORE, AND THE PERCENTAGE OF CIS PROGRESS IS INDICATED AS 74.67 %.
Monday, December 15, 2008
CIS GOT 1 MORE
PARAPETS MOVE ON 3 PATH
PARAPET GANTRY NO.1 IS NOW REACHING THE SPAN OF P131-P132. MEANWHILE PARAPET GANTRY NO.2 IS BUSY ERECTING THE PARAPETS ON PP3-PP4. ON THE OTHER SIDE, PARAPET GANTRY NO.3 WILL BE WORKING ON THE COMPLETED SPAN CHASING LAUNCHER GIRDER NO.2 WHICH IS ON P42-P43.
CASTING UPDATE
Monday, December 1, 2008
INDIA ELECTION
LG NO.2 CONTINUES ITS SCHEDULE TO WORK ON NEXT SPAN AFTER BEING STOPPED DUE TO INDIA'S ELECTION ON 29th NOVEMBER IN ORDER TO AVOID ANY INCONVINIENCE CIRCUMSTANCES. AFTER AN ATTACK IN MUMBAI, SECURITY HAS BEEN EMPHASIZED FROM PUBLICS TO FACILITIES AND BUILDINGS TO CONSTRUCTION AREA. SO FAR, THERE WAS NO INCIDENT, BUT LG NO.2 IS CONCERNING ON THE COMING SPANS EVEN THE LAST 6 PIERS TOWARDS NANGLOI STATION IS STILL NOT BAING CONSTRUCTED.
LG NO.1 CLOSES ITS DIARY