LAST SATURDAY, 21st OF MARCH 2009, LAUNCHING GIRDER NO.2 WAS BEING AUTOLAUNCHED. 2 PIERS PARTICULARLY NAMED P35 AND P34 OF THE SO CALLED HOLD ON AREA ARE NOW FINISH ITS CURING PERIOD, APPARENTLY READY TO SUPPORT LOAD. BY MONDAY, ONE SEGMENT IS LIFTED FOR LOADING TEST. MEANWHILE, THE THIRD PIER OF P33 SEEMS STANDING STRAIGHT WITHOUT ITS HEAD WHICH SOON BE CONSTRUCTED.
Wednesday, March 25, 2009
BACK ON SAIL
LAST SATURDAY, 21st OF MARCH 2009, LAUNCHING GIRDER NO.2 WAS BEING AUTOLAUNCHED. 2 PIERS PARTICULARLY NAMED P35 AND P34 OF THE SO CALLED HOLD ON AREA ARE NOW FINISH ITS CURING PERIOD, APPARENTLY READY TO SUPPORT LOAD. BY MONDAY, ONE SEGMENT IS LIFTED FOR LOADING TEST. MEANWHILE, THE THIRD PIER OF P33 SEEMS STANDING STRAIGHT WITHOUT ITS HEAD WHICH SOON BE CONSTRUCTED.
Saturday, March 21, 2009
RECENT VIEW
Tuesday, March 17, 2009
C.I.S COMPLEMENTATION
YESTERDAY, 16th OF MARCH THE LAST SPAN OF CAST IN-SITU SPAN WAS CONCRETED. THIS SPAN IS COMPLEMENTING THE 15 CIS SPANS AT MUNDKA. THE CONCRETING STARTED BY AFTERNOON, AND LAST FOR SEVERAL HOURS. AS A LAST SPAN, MOST WORKERS CAME TO SEE, AS I BROUGHT TOGETHER ON HOW THE FIRST IS DONE BY. THIS SPAN OF PP140-PP141 IS A TRAPEZIUM IN SHAPE WITH A WIDTH OF 9180mm AND 11892mm FOR EACH SOUTH AND NORTH CHAINAGE, PARTICULARLY AND A TOTAL LENGTH OF 25 METERS. NO SUCH BAD INCIDENT HAPPENED.
Thursday, March 12, 2009
FRENZY MORE ABATED
THE EXIT LINE, FROM MUNDKA STATION TO THE DEPO IS NOW PLACING THE LAST FEW PARAPET TO GO BEFORE HANDING IT OVER TO THE LAING-INDU JV. DUE TO A LIMITED SPACE, CRANES WERE USED. SO FAR, ONLY 1 SPAN MORE BALANCE TO ERECT THE PARAPET.
LAST POUR IS AROUND THE CORNER
THE LAST SPAN IN CAST IN-SITU SITE, PP140-PP141 IS NOW PREPARING ITS LAST REBAR WORK BEFORE IT RECEIVES THE LAST POUR TO COMPLETE THE WHOLE PERCENTAGE OF CAST IN-SITU WORK OF 15 SPANS. OVERALL PERCENTAGE OF COMPLETION IS 98%. THE CONCRETING IS PLANNED TO TO BE THIS WEEK.