Thursday, January 8, 2009

FINAL BIT

Photo 1 : steep spans towards the ramp.

Photo 2 : Final touch near Surajmal Stadium.

AFTER THE FIRST ROUTE OF NANGLOI RLY-RAJDHANI PARK, IT IS NOW SURAJMAL STADIUM-NANGLOI WILL BE THE SECOND. A FEW PARAPETS SEEMS TO BE ERECTED ON THE LAST SPAN, MEANWHILE THE STICHING PROGRESS IS UNDERGOING ON ITS PREVIOUS.

PARAPET GANTRY NO.1 PLANS TO COMPLETE THE REST WITHIN A FEW DAYS. PARAPET GANTRY NO.2 SEEMS TO BE INDUCED, IT IS NOW ERECTED THE PARAPETS ON ITS FIRST CIS SPAN OF CP133-PP134.

STEEPY SIX SPANS ON OLD LG NO.2 SITE WERE AMONG THE PLACE WHERE PARAPET IS BEING LOCATED. P147A-P148A RECEIVED ITS PARAPET NOT BY GANTRY BUT CROWNED BY CRANE, MANUALLY DUE TO THE INCLINATION.

Wednesday, January 7, 2009

FADES AWAY

Photo 1 : Bitter sweet memory.

Photo 2 : Current view.

NOTHING IS LOST OR BEING STOLEN, JUST TO MENTION THAT LAUNCHING GIRDER NO.1 OR LG NO.1 HAS BEEN DISMANTLED. TAKING 2 WEEKS, STARTS WITH THE FRONT SUPPORT AND REAR SUPPORT IS THE LAST COMPONENT BEING DELIVERED TO THE YARD. THE ONLY UNDERGOING LAUNCHING GIRDER IS LG NO.2WHICH MAY HAVE 5 SPANS MORE TO BE COMPLETED BEFORE REACHING THE HOLD ON AREA. SO FAR, THOSE 6 PIERS WILL BE CONSTRUCTED AS THE DEMOLITION WAS JUST DONE.

Tuesday, January 6, 2009

ANOTHER CIS SPAN CASTED

Photo 1 : Wait for curing period.


THE SECOND LIFT CONCRETE LAYER WAS POURED ON PP137A-P138A ON FRIDAY, 2nd DEC 08 AND THIS SO CALLED LAST RAJDHANI-MUNDKA SPAN IS A SINGLE TRACK SPAN CONNECTING THE MAIN LINE TO THE DEPO PASSING THROUGH THE MUNDKA STATION. LOCATED AT THE CORNER OF THE DIVERTED ROAD, SPACES WERE THE MAIN CONCERNED. CONCRETING IS DONE AT NIGHT IN ORDER TO MINIMIZE THE RISK OF ACCIDENT, ESPECIALLY TO THE PUBLIC AND MOTORIST.

Saturday, January 3, 2009

NEW YEAR

Photo 1 : View of Mundka at dusk.


1st JANUARY IS BACK, HAPPY NEW YEAR TO ALL THE VIEWERS.
WISHING YOU ALL THE HAPPINESS AND MAY 2009 BRINGS YOUR THE LUCKIEST EVER SUCCESS.

Monday, December 15, 2008

CIS GOT 1 MORE

Photo 1 : PP146A-PP147A, ready to be lowered.

Photo 2 : PP143-PP144 before casting.

Photo 3 : PP143-PP144 after casting, is on curing period.


Photo 4 : PP137A-P138A is ready to receive its weight.

ONE MORE SPAN AT CAST IN-SITU SITE, CUMMULATIVELY 11 SPANS CASTED. THE SECOND LAYER CONCRETE POURED YESTERDAY DEC13 ON SPAN PP143A-PP144A. MEANWHILE, THE LAST SPAN OF CIS I IS PLANNED FOR ITS 1st CASTING AROUND THIS WEEK BECAUSE MOST OF THE REINFORCEMENT IS READY AND SOME OF THE INNER SHUTTERS WERE START PLACED. SO, WITH 3 BALANCES MORE, AND THE PERCENTAGE OF CIS PROGRESS IS INDICATED AS 74.67 %.

PARAPETS MOVE ON 3 PATH

PARAPET GANTRY NO.1 IS NOW REACHING THE SPAN OF P131-P132. MEANWHILE PARAPET GANTRY NO.2 IS BUSY ERECTING THE PARAPETS ON PP3-PP4. ON THE OTHER SIDE, PARAPET GANTRY NO.3 WILL BE WORKING ON THE COMPLETED SPAN CHASING LAUNCHER GIRDER NO.2 WHICH IS ON P42-P43.

CASTING UPDATE

Photo 1 : Among the balances at yard.


THE LATEST UPDATE SAYING THAT TOWARDS THE LAST EXISTED PIER ON NANGLOI RAILWAY STATION TO NANGLOI STATION OF P35, THERE ARE 10 SEGMENTS BALANCE TO CAST. CASTING OF PARAPET IS NOW BEING CONCERNED ON CURVE SPAN AND NON-STANDARD PARAPET.

Monday, December 1, 2008

INDIA ELECTION

LG NO.2 CONTINUES ITS SCHEDULE TO WORK ON NEXT SPAN AFTER BEING STOPPED DUE TO INDIA'S ELECTION ON 29th NOVEMBER IN ORDER TO AVOID ANY INCONVINIENCE CIRCUMSTANCES. AFTER AN ATTACK IN MUMBAI, SECURITY HAS BEEN EMPHASIZED FROM PUBLICS TO FACILITIES AND BUILDINGS TO CONSTRUCTION AREA. SO FAR, THERE WAS NO INCIDENT, BUT LG NO.2 IS CONCERNING ON THE COMING SPANS EVEN THE LAST 6 PIERS TOWARDS NANGLOI STATION IS STILL NOT BAING CONSTRUCTED.

LG NO.1 CLOSES ITS DIARY

Photo 1 : Front support has been de-erected.


BY STRESSING DONE AT FRIDAY NIGHT OF 28th NOVEMBER, LAUNCHING GIRDER NO.1 IS NOW BEGIN TO BE DISMANTLED. FROM RAJDHANI PARK TO MUNDKA, LG NO.1 HAD DONE 39 SPANS.

Monday, November 10, 2008

YAMUNA CROSSING BRIDGE

Photo 1 : Pier cap on river bank

Photo : The pier

Photo 3 : View of a span

Photo 4 : Bridge and the river

Photo 5 : View on span

Photo 6 : View on parapet

Photo 7 : View towards the depo

Photo 8 : View of the river from the bridge

Photo 9 : Underneath the segments

Photo 10 : Another view

Photo 11 : Long straight spans, usually the delta will be submerged by water during monsoon

Photo 12 : Another view

Photo 13 : A part of the bridges headings to cross the river

Photo 14 : Another view