TODAY, THE LAUNCHING GIRDER OF LG NO.2 IS LIFTING THE SEGMENTS OF P30-P31. THIS SPAN HAS 11 SEGMENTS,OR 28 METERS LENGTH. THIS IS OUR SECOND LAST SPAN, IS BELIEVED TO BE STRESSED BY TOMORROW NIGHT OR DAY AFTER TOMORROW. MEANWHILE, THERE WAS A SAFETY CHECKING HELD AT SITE, AND OF COURSE OUR LAUNCHER IS A COMPULSORY CHECK-POINT FOT THEM, FROM OUR CLIENT DELHI METRO RAILWAYS CORPORATION.
Wednesday, April 15, 2009
GETTING CLOSER
TODAY, THE LAUNCHING GIRDER OF LG NO.2 IS LIFTING THE SEGMENTS OF P30-P31. THIS SPAN HAS 11 SEGMENTS,OR 28 METERS LENGTH. THIS IS OUR SECOND LAST SPAN, IS BELIEVED TO BE STRESSED BY TOMORROW NIGHT OR DAY AFTER TOMORROW. MEANWHILE, THERE WAS A SAFETY CHECKING HELD AT SITE, AND OF COURSE OUR LAUNCHER IS A COMPULSORY CHECK-POINT FOT THEM, FROM OUR CLIENT DELHI METRO RAILWAYS CORPORATION.
PARAPET UPDATES
PARAPET CASTING WAS DONE, CURRENTLY ERECTION IS GOING ON. PATH OF NANGLOI RAILWAY STATION TO NANGLOI STATION SEEMS TO BE ALMOST BUSY AS THE PARAPET GANTRY IS CHASING THE LAUNCHING GIRDER QUITE CLOSE. STICHING IS DONE AT P34-P35, TWO SPANS BEHIND.
AT CIS II, ONLY 3 SIDES OF PARAPET ERECTION ARE YET COMPLETED, 2 SIDES OF THE LATEST CONCRETED SPAN AND ONE SIDE OF PP142-PP143. IN THE MEANTIME, CAST IN-SITU PARAPET WILL BE READY SOON AT THE END OF P158 AND PP135.
Tuesday, April 14, 2009
THIRD LAST UNDERGOING
LAUNCHING GIRDER NO.2 IS NOW STANDING ON P32-P31, THE THIRD LAST SPAN. IT MEANS 2 MORE SPANS TO GO, WITH APPROXIMATELY 98% OF SEGMENTAL BOX GIRDER ERECTION IS COMPLETED. THIS SPAN CONSISTS 10 SEGMENTS, AFTER ALL BEING LIFTING, BALANCE OF 20 SEGMENTS ARE STILL AT CASTING YARD.
Friday, April 10, 2009
GOODBYE SPRING
Photo 2 : Wheat is getting mature and will be harvested within a few weeks later.
A FEW DAYS AGO, IT WAS CLOUDY IN NEW DELHI. OBVIOUSLY, THE COMULUNIMBUS COVERS THE GROUND AGAINST SUNLIGHT. IT WAS FULL OF LOADS, WATER THAT WILL BE SPREAD AWAY AS RAIN. IT WAS SO SUDDEN ABOUT LESS THAN AN HOUR, THAT BELIEVED SUMMER ENDS. THEN, THE SIRUS WHICH HIGHER ON ALTITUDE CAME ALONG. LIGHT IS BLAZING THROUGH THIS SIRUS CLOUD, BROUGHT HEAT AND TEMPERATURE RISES HIGHER UP.
NOWADAYS, TEMPERATURE IS RECORDED UP TO 47 DEGREE CELCIUS IN THE AFTERNOON. EVEN LA NINA HITS THE EARTH, CATASTROPHIES OCCURED IN MANY PLACES BUT NOT MUCH DIFFERENT IN NEW DELHI UNLESS THE WINTER WAS NOT SO CHILL AND SUMMER LAST SOONER COMPARE TO THE SAME SEASONS LAST YEAR. OFFICIALLY SUMMER IS COMING.
Wednesday, April 8, 2009
GLIMPSES BY END SPRING
Sunday, April 5, 2009
BACK FOR GOOD
Wednesday, March 25, 2009
BACK ON SAIL
LAST SATURDAY, 21st OF MARCH 2009, LAUNCHING GIRDER NO.2 WAS BEING AUTOLAUNCHED. 2 PIERS PARTICULARLY NAMED P35 AND P34 OF THE SO CALLED HOLD ON AREA ARE NOW FINISH ITS CURING PERIOD, APPARENTLY READY TO SUPPORT LOAD. BY MONDAY, ONE SEGMENT IS LIFTED FOR LOADING TEST. MEANWHILE, THE THIRD PIER OF P33 SEEMS STANDING STRAIGHT WITHOUT ITS HEAD WHICH SOON BE CONSTRUCTED.
Saturday, March 21, 2009
RECENT VIEW
Tuesday, March 17, 2009
C.I.S COMPLEMENTATION
YESTERDAY, 16th OF MARCH THE LAST SPAN OF CAST IN-SITU SPAN WAS CONCRETED. THIS SPAN IS COMPLEMENTING THE 15 CIS SPANS AT MUNDKA. THE CONCRETING STARTED BY AFTERNOON, AND LAST FOR SEVERAL HOURS. AS A LAST SPAN, MOST WORKERS CAME TO SEE, AS I BROUGHT TOGETHER ON HOW THE FIRST IS DONE BY. THIS SPAN OF PP140-PP141 IS A TRAPEZIUM IN SHAPE WITH A WIDTH OF 9180mm AND 11892mm FOR EACH SOUTH AND NORTH CHAINAGE, PARTICULARLY AND A TOTAL LENGTH OF 25 METERS. NO SUCH BAD INCIDENT HAPPENED.
Thursday, March 12, 2009
FRENZY MORE ABATED
THE EXIT LINE, FROM MUNDKA STATION TO THE DEPO IS NOW PLACING THE LAST FEW PARAPET TO GO BEFORE HANDING IT OVER TO THE LAING-INDU JV. DUE TO A LIMITED SPACE, CRANES WERE USED. SO FAR, ONLY 1 SPAN MORE BALANCE TO ERECT THE PARAPET.