Photo 2 : Bottom shutters placed on span PP143-PP144.
Photo 3 : Progress for erecting the moulds of span PP146A-P147A.
OVERALL 15 SPANS SUPPOSE TO BE CONSTRUCTED BY CAST IN-SITU METHOD. SO FAR, 7 OF THEM WERE FULLY COMPLETED. 2 MORE SPANS ARE ALMOST DONE, ONLY WAIT TO BE LOWERED. MEANWHILE, 3 SPANS ARE UNDER CONSTRUCTION WITH 2 SPANS AT CIS II SITE WHICH IS PROGRESSING ON INSTALLING THE SHUTTERS AND ANOTHER ONE (AT CIS I) IS FOCUSING TO ERECT THE LAST A FEW CRIBS. WITH BALANCE OF 3 SPANS LEFT, PERCENTAGE OF COMPLETION FOR THE WHOLE CAST IN-SITU PROGRESS IS 68 %.