THIS IS AN UNOFFICIAL BLOG OF BC9 PROJECT

.

Wednesday, October 22, 2008

FLAME BLAZES THE RAMP

Photo 1 : Front view of U5.


Photo 2 : Side view of U4.

Photo 3 : View of the ramp from erected span of P152A-P153A.

Photo 4 : Shutters of U3.

THE SUN DANCES DIZZILY AND LIGHTS THE DAYTIME. HENCE, THE FLAME IS BLAZING THE SKIN. THOSE EXTREME DAYS WASN'T STOP THE WORK OF RAMP. OVERALL COMPLETION IS ROUGHLY ESTIMATED, ABOUT 70 %. THE RAMP SITE IS THE FINAL TRACK LEADS THE METRO LINE TO THE DEPO. IT IS DIVIDED INTO 5 UNITS, FROM UNIT 1 (U1) TO UNIT 5 (U5). UNIT 4 AND UNIT 5 WERE COMPLETED. MEANWHILE, MOST OF THE SHUTTERS OF UNIT 3 HAD BEEN ERECTED, ONLY NOW EMPHASIZING ON REINFORCEMENT PROGRESS.