Photo 1 : Bulkhead for PP139A-PP140A.
Photo 2 : Bringing up the mould for PP143A-PP144A.
JUST TO INFORM THE LATEST PROGRESS AT CIS, OVERALL 85% COMPLETED. PP139A-PP140A WAS JUST DOING LITTLE PREPARATION BEFORE GETTING IT FIRST LAYER CONCRETE, PLANNED TO BE ON FRIDAY 23rd JAN 2009. NEXT IS PP140-PP141, GOT ITS STAGING SYSTEM. OUTER MOULD FOR PP143A-PP144A WAS JUST STARTED AND STILL UNDERGOING.
MEANWHILE, CIS I WAS JUST CLOSED AND THE DISMANTLING OF ITS CRIB STAGING WAS FINISHED TO LET THE PARTNER VENTURE CONSTRUCT THEIR SPAN, NEXT TO THE LATEST CASTED SPAN IN ORDER TO GIVE WAY FOR ROAD DIVERSION.