Thursday, January 22, 2009

TWO SPANS FURTHER

Photo 1 : LG No.2 finished lifting yesterday and prepare its stressing part currently.

Photo 2 : Piling work to construct the rest 6 piers.

RECENTLY, STRESSING WORK IS STILL ON PROGRESS AT LAUNCHING GIRDER NO.2. SPAN OF P38-P39 WILL BE FULLY ERECTED AND LOWERED ON ITS SHEAR KEY PADESTAL BY THURSDAY. NEXT COMING IS TWO SPAN OF 10 SEGMENTS, THEN REACHING THE PIER OF P36.

BALANCE OF SEGMENT TO BE ERECTED IS 91nos. 69 SEGMENTS STORED AT CASTING YARD AND ANOTHER 22 IS BALANCE TO CAST. IT MEANS THE COMPLETION PERCENTAGE OF SEGMENT ERECTION IS 94%.

AFTER DEMOLITION, OUR JV PARTNER SEEMS TO BE RUSHING THEIR WORK TO COMPLETE THE PILINGS.