
Photo 1 : Span PP134-PP135

Photo 2 : Span CP133-PP134 ready to be lowered

Photo 3 : Span PP136-PP137
SO FAR, ONLY 1 CIS SPAN OF CP133-PP134 FULLY COMPLETED. 2 NEW SPANS ON CRIBS PREPARATION (PP136-PP137 AND PP145-PP146), ANOTHER 2 SPAN ALREADY EXCEED 30% COMPLETION WHERE PP135-PP136 HAS DONE ITS FIRST LAYER CASTING ON 21ST APRIL (57%) AND PP134-PP135 CONTINUES FOR INSTALLING THE SHUTTERS (31%).
No comments:
Post a Comment