Thursday, September 4, 2008

PARAPET TOOK PLACE

Click on above table for enlargement.


MOST VISIBLY PROGRESS SEEN AT PARAPET ERECTION, AS GANTRY NO.2 IS CHASING LAUNCHING GIRDER NO.1 ON RAJDHANI-MUNDKA TRACK AND THE DISTANCE BETWEEN THEM IS GETTING CLOSER BY DAYS, JUST LESS THAN 13 SPANS. PARAPET GANTRY NO.1 FROM RAJDHANI-NANGLOI RAILWAY STATION TRACK WAS BEING REPLACED ON SPAN PP2-PP3 BUT IT WASN'T STARTING THE ERECTION PROGRESS YET. LAST BUT NOT LEAST, GANTRY NO.3 IS NOW RUNNING ON ITS 13th SPAN.
REGARDING TO THE ABOVE TABLE, 55.05 % OF STANDARD GAUGE PARAPETS HAVE BEEN ERECTED AT SITE, MEANWHILE 48.41 % OF ERECTION PROGRESS DONE AT BROAD GAUGE PARAPET SITE. OVERALL BALANCE OF PARAPET CASTING IS 16.32 %, AS UPDATED ON SEPT02.