THIS IS AN UNOFFICIAL BLOG OF BC9 PROJECT

.

Wednesday, August 13, 2008

DIARY CLOSED FOR LG3

Photo 1 : Last delivery to LG3.


Photo 2 : Moment captured during lifting of the last segment.

AT 2.00am ON 5th OF AUGUST 2008, FIRST PAIR OF THE TENDON OF SPAN SSS-P0 IS READY FOR STRESSING. ALL THE ARRANGEMENT PREPARED WELL, AND THE LAST PAIR STRESSED AT 10.00am ON NEXT DAY SHIFT ON 6th OF AUGUST. ON THE SAME DAY, ALL HOOKS RELEASED, IT MEANS SPAN LOWERING IS DONE. SO, LAUNCHING GIRDER NO.3 CLOSED ITS DAIRY FOR COMPLETING 26 SPANS OR 274 SEGMENTS HAVE BEEN ERECTED. FLASH BACK ON THE FIRST SPAN P26-P27 HAS BEEN ERECTED ON 29th JANUARY 2008, IT MEANS 7 MONTHS TO LET THE LAUNCHER STEPS ON THE END. SOME SPAN COMPLETED WITHIN 3 DAYS, SOME TAKE MORE. AVERAGE 4 AND A HALF DAYS FOR COMPLETING 1 SPAN. THANKS TO EVERYBODY!