Photo 2 : Second span ready for stressing on 12th of August.
FIRST SPAN OF THE THIRD PATH OF LG2, P54-P55 HAS BEEN ERECTED ON 30th JULY AFTER DAYS FOR ERECTING THE STEEL BOXES, PLACING THE SLIDERS AND MANY MORE. THEN, A FEW DAYS TAKEN TO ADD ANOTHER BOXES AT BACK AND MOVED FORWARD THROUGH AUTOLAUNCH. ON 12th OF AUGUST THE NEXT SPAN OF P53-P54 IS READY FOR STRESSING, IT IS BELIEVED WILL BE DONE ON DAY SHIFT OF 13th AUGUST. THIS HARD MOMENT WILL BE CONTINUED BY ADDING ANOTHER BOX TOGETHER SETTING UP THE REAR TROLLEY, THEN PLACING A FEW MORE COUNTERWEIGHTS AT THE BACK. THEN, THE THIRD AND COMING NEXT SPANS WILL BE NORMALLY EASIER, AS THE LAUNCHER MOVES BY ORDINARY AUTOLAUNCHING.
No comments:
Post a Comment