AS THE PARAPET ERECTION IMPROVES AND GOES FASTER, IT FORCES THE TWO TEAM OF GROUTING AND BEARING INSTALLATION TO DOUBLE UP THEIR WORKS. IF BEARING HAVEN'T BEEN INSTALL PROPERLY, PARAPET CANNOT BE ERECTED ON THAT PARTICULAR SPAN. AS UPDATED ON 6th AUGUST 2008, THE NUMBER OF BEARINGS INSTALLED (SPAN) IS 98. IT MEANS 63% HAS BEEN COMPLETED.