THIS IS AN UNOFFICIAL BLOG OF BC9 PROJECT

.

Wednesday, March 25, 2009

BACK ON SAIL

Photo 1 : 2 piers are now exist.

Photo 2 : Load testing.

LAST SATURDAY, 21st OF MARCH 2009, LAUNCHING GIRDER NO.2 WAS BEING AUTOLAUNCHED. 2 PIERS PARTICULARLY NAMED P35 AND P34 OF THE SO CALLED HOLD ON AREA ARE NOW FINISH ITS CURING PERIOD, APPARENTLY READY TO SUPPORT LOAD. BY MONDAY, ONE SEGMENT IS LIFTED FOR LOADING TEST. MEANWHILE, THE THIRD PIER OF P33 SEEMS STANDING STRAIGHT WITHOUT ITS HEAD WHICH SOON BE CONSTRUCTED.

No comments: