Photo 1 : Almost finish by dawn.
Photo 2 : Engineer faiz.
Photo 3 : A few moment before the casting is being started.
YESTERDAY, 16th OF MARCH THE LAST SPAN OF CAST IN-SITU SPAN WAS CONCRETED. THIS SPAN IS COMPLEMENTING THE 15 CIS SPANS AT MUNDKA. THE CONCRETING STARTED BY AFTERNOON, AND LAST FOR SEVERAL HOURS. AS A LAST SPAN, MOST WORKERS CAME TO SEE, AS I BROUGHT TOGETHER ON HOW THE FIRST IS DONE BY. THIS SPAN OF PP140-PP141 IS A TRAPEZIUM IN SHAPE WITH A WIDTH OF 9180mm AND 11892mm FOR EACH SOUTH AND NORTH CHAINAGE, PARTICULARLY AND A TOTAL LENGTH OF 25 METERS. NO SUCH BAD INCIDENT HAPPENED.
Tuesday, March 17, 2009