WHEN THE 7th CAST IN-SITU SPAN GOT IT FIRST LIFT, THE COMPLETED WORK PERCENTAGE OF CIS PROGRESS IS NOW UP TO 48.86 %. NOT MUCH HAPPEN AT CIS I AS ONLY WORK DONE FOR SPAN LOWERING, BUT MOST ATTENTION PAID ON CIS II. PP144-PP145 IS NOW ON PROGRESS FOR COMPLETING THE REST REBARS BEFORE THE SECOND LIFT OF CONCRETE LAYERED ON IT. ALL SET OF OUTER SHUTTERS HAVE BEEN ERECTED ON PP141-PP142 AND THE REBARS IS NOW RUNNING ON. APPROXIAMATELY, CRIBS INSTALLATION FOR SPAN PP140-PP141 WAS COMPLETED.
Showing posts with label CIS UPDATES. Show all posts
Showing posts with label CIS UPDATES. Show all posts
Tuesday, September 9, 2008
Wednesday, August 13, 2008
CIS UPDATES
Photo 1 : First casted span located at CIS II site.AS UPDATED, SO FAR 5 SPANS OF CAST IN-SITU HAVE BEEN CONCRETED. TWO OF THEM ARE NOW ON PREPARATION FOR STRESSING AND THEN BEING LOWERED. SPAN PP145A-PP146A AT CIS II USED TO COMPLETE THE FIRST LAYER CASTING ON 17th JULY, PROCEED THE SECOND LAYER 12 DAYS AFTER ON 29th JULY. MEANWHILE SPAN PP136A-PP137A AT CIS I GOT ITS FIRST LAYER ON 19th JULY, AND SECOND LAYER POURED ON 29th JULY.
IN THE MEANTIME, ANOTHER SPAN AT CIS II PP142A-PP143A IS PLANNED TO BE CASTED JUST AROUND THE CORNER, MAYBE ON THE DAY 13th OF AUGUST 2008. ANOTHER 2 SPANS ARE NOW ON PROGRESS IS PP144A-PP145A AND PP141A-PP142A, WHICH NOW SETTING THE BOTTOM SHUTTERS AND JUST FINISH THE CRIBS INSTALLATION, PARTICULARLY. AS CALCULATED, CAST IN-SITU PROGRESS IS NOW REACHING ITS 45% OF COMPLETION. IT SHOWS SOME SPEED UP COMPARE TO LAST A FEW MONTHS PROGRESS.
Subscribe to:
Posts (Atom)