Photo 1 : Grouted tendon.Wednesday, August 13, 2008
GROUTING AND BEARING INSTALLATION
Photo 1 : Grouted tendon.THE RAMP
Photo 1 : View taken on 4th July 2008.
Photo 2 : View taken on end of May.
THE RAMP IS CONNECTING THE EXIT LINE TO THE DEPO, CONSISTS 5 UNITS OR PARTS, NAMED U1 TO U5. EACH UNIT HAS ITS OWN PCC, RAFT AND LIFT. NUMBER OF LIFTS DEPEND TO THE DESIGN. FOR EXAMPLE, U1 AND U2 HAVE 4 LIFT WHERE U1 IS CONNECTING THE RAMP TO THE EXISTED 6 EXIT LINE. SO FAR, ALL PCC AND RAFT OF ALL UNITS HAVE BEEN CONCRETED. FIRST LIFT OF ALL UNITS EXCEPT U1 ALSO HAVE BEEN CASTED. THE LATEST UPDATED, SECOND LIFT OF U4 AND U5 ARE ALSO CASTED. AS A ROUGH CALCULATION, 49.5% OF WORK DONE.
STANDING IN THE EYES
Photo 1 : The great look of the new building of MTD Group.GLUE
LG2 GIVES 2
Photo 2 : Second span ready for stressing on 12th of August.
FIRST SPAN OF THE THIRD PATH OF LG2, P54-P55 HAS BEEN ERECTED ON 30th JULY AFTER DAYS FOR ERECTING THE STEEL BOXES, PLACING THE SLIDERS AND MANY MORE. THEN, A FEW DAYS TAKEN TO ADD ANOTHER BOXES AT BACK AND MOVED FORWARD THROUGH AUTOLAUNCH. ON 12th OF AUGUST THE NEXT SPAN OF P53-P54 IS READY FOR STRESSING, IT IS BELIEVED WILL BE DONE ON DAY SHIFT OF 13th AUGUST. THIS HARD MOMENT WILL BE CONTINUED BY ADDING ANOTHER BOX TOGETHER SETTING UP THE REAR TROLLEY, THEN PLACING A FEW MORE COUNTERWEIGHTS AT THE BACK. THEN, THE THIRD AND COMING NEXT SPANS WILL BE NORMALLY EASIER, AS THE LAUNCHER MOVES BY ORDINARY AUTOLAUNCHING.
CIS UPDATES
Photo 1 : First casted span located at CIS II site.DIARY CLOSED FOR LG3
Photo 1 : Last delivery to LG3.
Photo 2 : Moment captured during lifting of the last segment.
Monday, July 14, 2008
CIS Upadate
Photo 1 : Figure of Span PP136A-PP137A which on preparation before casting.
Photo 2 : The second concreted span of PP135A-PP136A is already lowered.
Photo 3 : Launcher Girder No.1 is keep running on the rest 10 spans before reaching CIS I site area.
BY MID JULY, 2 MOULD OF CIS SPANS ARE READY TO BE CASTED JUST AROUND THE CORNER. THERE ARE PP136A-PP137A AND PP145A-PP146A PARTICULARLY LOCATED AT CIS I AND CIS II. OVERALL 27.8% OF WORK DONE.
CROSSING OVER PORTAL PIERS
Photo 1 : Back view from Launching Girder No.3 towards the completed spans.
Photo 2 : Front view captured from LG3 looking towards the rest piers.PARAPET GANTRY NO.3 LAUNCHED
Photo 1 : Among the earliest parapet erected by Parapet Gantry No.3
Photo 2 : View captured, showing the path created by LG3 for this new gantry to work on.
PARAPET GANTRY NO.3 IS NOW WORKING ON THE TRACK FROM NANGLOI STATION TOWARDS SURAJMAL STADIUM. THIS IS THE BUSIEST LOCATION ALONG BC9 PROJECT WHICH 24 HOURS VEHICLES MOVE ON ROAD, TRAFFIC JAM IS FREQUENTLY SEEN. THE ROUTE IS THE MAIN NATIONAL HIWAY CONNECTING NEW DELHI TO THE BORDER OF BAHADUR GARH IN THE STATE OF HARYANA. THIS MOMENT, THE WAY TO LIFT UP THE PARAPET IS NOW CHANGED. THE USE OF HYDRA IS PRACTICALLY DISTURBING THE TRAFFIC AND NOT MORE ACCESSIBLE, SO DIRECTLY GANTRY WILL ADJUSTS THE WINCH TO LET IT HOOKS THE PARAPET PIECE UP FROM THE TRAILER. CONSEQUENTLY, THE COMPANY DECIDES TO REDUCE THE NUMBER OF HYDRAS HIRED AND IT SEEMS TO BE ECONOMIC.