Photo 2 : Autolaunching almost done as the workers completing the last preparation.
Thursday, May 29, 2008
JUBILEE 100
Monday, May 26, 2008
SPICES OF DELHI-part 1
Photo 1 : Malaysian Team, 7 among the 9 fellows.
WATCHING MISTRESS OF SPICES, STARRING AISHWARYA RAI, WE KNOW HOW FAMILIAR IS INDIA WITH SPICES. EVERY FOOD MIXED WITH VARIETY OF SPICES. ONCE TOUCHING THE TOUGUE, WE CAN TASTE IT; EITHER IT IS SWEET, SOUR, SALTY OR SPICY? STEP ON DELHI, LET US TASTE AND REALIZE WHAT LIES ON?
Photo 3 : Sunset at Yamuna River.
Photo 4 : The Glitter of modern Delhi at night.
Photo 5 : Mahatma Gandhi.
Friday, May 23, 2008
Thursday, May 22, 2008
BC9 WILL CHANGES NANGLOI
THE UNSYSTEMATIC TRAFFIC CONTROL IS NOT JUST THE MAIN ISSUE, BUT PUBLIC SAFETY. LIGHT RAIL SYSTEM PROVIDES SAFE AND CONVINIENT JOURNEY. AT THIS JUNCTION (NEAR LG3), A FLYOVER OF NH10-NANGLOI IS UNDER CONSTRUCTION.
HOPEFULLY, THE BUSY AND NOISY OF NANGLOI WILL TURNS BETTER AS THE BC9 PROJECT DONE, AS PLANNED TO BE COMPLETED AS A TRIBUTE FOR DELHI AS THE HOST FOR COMMONWEALTH GAMES IN 2010.
Wednesday, May 21, 2008
TEN MORE TO GO
NEW POINT STARTED ON
Saturday, May 10, 2008
2nd CIS SPAN CASTED
Photo 1 : Concrete poured into mould of span PP135A-PP136A
ON MAY 09, THE SECOND CAST IN-SITU SPAN SUCCESSFULLY CASTED. THIS PP135A-PP136A SPAN STARTED CONCRETING AT 1.30pm AND FINISHED THE LAST CONCRETE DROP AT 9.30pm. THE VOLUME OF CONCRETE USED FOR THIS SECOND LAYER AMOUNTED AS 106 CUBIC METRE. LUCKILY, THE PROGRESS GOES SMOOTHLY WITHOUT ANY INCONVINIENCE EVEN ACCIDENT.
Photo 2 : Cribs for span PP145A-PP146A
A DAY IN ADVANCE, CRIBS INSTALLATION OF SPAN PP145A-PP146A IS COMPLETED AND NEXT FOCUSING ON SETTINGS OF THE MOULD.LAST PIECE COUNTDOWN
Photo 1 : Last piece lifted up by crane
Photo 2 : The figure of the completed span with parapet at Mundka
ON MAY 08, GANTRY NO.2 (MUNDKA STATION TOWARDS DEPOT) IS SCHEDULED TO FINISH ERECTION OF BROAD GAUGE PARAPETS. HOWEVER, A PROBLEM OCCURED DUE TO A GANTRY BREAKDOWN. TIME IS GOLDEN, THE ENGINEERS DECIDED TO COMPLETE THE PROGRESS BY USING A CRANE. BEFORE LUNCH, ALL LAST PIECES WERE COMPLETELY ERECTED AND FOLLOWED BY STICHING ALL THE JOINTS WITH CONCRETE. GANTRY NO.2 PLANNED TO BE DISMANTLED AND REINSTALL ON A NEW BEGINNING POINT AT RADJHANI PARK ON SPAN P96-P97, HEADINDS TOWARD MUNDKA STATION BY FOLLOWING THE TRACK OF LAUNCHER NO.1. IN THE MEAN TIME, THIS SEGMENT LAUNCHER IS NOW STARTING TO LIFT SEGMENTS ON SPAN P115-P116.
Thursday, May 1, 2008
CASTING YARD
Photo 1 : Casting bed, 10 tonne gantry and transit mixer
Photo 2 : Parapets stored at yard waiting to be erected at site
Photo 3 : Batching Plant -aggregates size 20mm and 10mm
Photo 4 : When the casted segment achieves its adequate lifting strength, it will be moved to another place for curing purpose by using 80tonne gantry
CAST IN-SITU
Photo 1 : Span PP134-PP135
Photo 2 : Span CP133-PP134 ready to be lowered
Photo 3 : Span PP136-PP137
PARAPET INSTALLATION
Photo 2 : Figure of a parapet gantry and erection progress
Photo 3 : Parapet erected by using tent buckle