Thursday, May 29, 2008

JUBILEE 100

IN A FEW DAYS, WE ARE GOING TO TEAR THE CALENDAR SHEET OF MAY. THEN JUNE IS COMING. LAUNCHING ACTIVITY IS NOW MOVING FORWARD BY AUTOLAUNCHING, GAINING TASKS OF LOAD BY SPREADING THE SLIDERS TO LIFT THE SEGMENTS AND THEN APPROVING THE TRUSTWORTHY BY TIGHTENING THEM THROUGH STRESSING THE TENDONS.
HOPEFULLY BY CLOSING THE LAST DATE OF MAY, 100 ERECTED SPANS WILL BE ACHIEVED. ON MAY28, 97 SPANS ERECTED. MEANWHILE, THE LATEST PROGRESS BY EACH LAUNCHING SITE IS POSITIVELY SEEN. LG NO.1 IS NOW ON LIFTING THE LAST FEW SEGMENTS AND BOTH LG NO.2 AND LG NO.3 FINISHED THE AUTOLAUNCHING.


Photo 1 : Lifting segments at LG No.1


Photo 2 : Autolaunching almost done as the workers completing the last preparation.