Photo 1 : Casting bed, 10 tonne gantry and transit mixer
Photo 2 : Parapets stored at yard waiting to be erected at site
Photo 3 : Batching Plant -aggregates size 20mm and 10mm
Photo 4 : When the casted segment achieves its adequate lifting strength, it will be moved to another place for curing purpose by using 80tonne gantry
UPDATED AS ON 29TH APRIL, SEGMENT CASTING FOR APRIL DROPS TO 63 WITH CUMMULATIVE NUMBER OF 1237. PARAPET CASTING UP TO 2046 CUMMULATIVELY WITH 304 NUMBERS CASTED IN APRIL. CABLE TROUGH FOR BASES AND COVERS TOTALLY 21928 WERE CASTED.