Photo 1 : Last piece lifted up by crane
Photo 2 : The figure of the completed span with parapet at Mundka
ON MAY 08, GANTRY NO.2 (MUNDKA STATION TOWARDS DEPOT) IS SCHEDULED TO FINISH ERECTION OF BROAD GAUGE PARAPETS. HOWEVER, A PROBLEM OCCURED DUE TO A GANTRY BREAKDOWN. TIME IS GOLDEN, THE ENGINEERS DECIDED TO COMPLETE THE PROGRESS BY USING A CRANE. BEFORE LUNCH, ALL LAST PIECES WERE COMPLETELY ERECTED AND FOLLOWED BY STICHING ALL THE JOINTS WITH CONCRETE. GANTRY NO.2 PLANNED TO BE DISMANTLED AND REINSTALL ON A NEW BEGINNING POINT AT RADJHANI PARK ON SPAN P96-P97, HEADINDS TOWARD MUNDKA STATION BY FOLLOWING THE TRACK OF LAUNCHER NO.1. IN THE MEAN TIME, THIS SEGMENT LAUNCHER IS NOW STARTING TO LIFT SEGMENTS ON SPAN P115-P116.